HANOVER LTN PILOT PROJECT: TASKS & TIMELINE

to be delivered over a single phase or a number of phases - dependent on options appraisal outcomes - and budget availability. The first phase would deliver the key LTN measures and modal filters using LTP 2021-22. A second Phase (2022) would allow for complementary measures to be introduced with LTP budget 2022-23

 

Milestones/tasks

START

FINISH

Procure/access community engagement mapping software

February 2021

April 2021

Procure contract and appoint consultancy support

March 2021

April 2021

Conduct project data baseline data such as traffic surveys including consultation (stakeholder and community) issues opportunities mapping

April 2021

August 2021

Options identification / high level costings /

May 2021

September 2021

ETS report - Preferred option / project delivery plan agreed

October or November (ETS) tbc

 

Detailed design Phase 1

October 2021

March 2022

Construction

November 2021

December 2021

Experimental Traffic Regulation Order (ETRO) consultation (and initial monitoring) period

December 2021

May 2022

Phase 2 detailed design

February 2022

March 2022

Phase 2 construction

April 2022

May 2022

Phase 3 ETRO public consultation period

July 2022

January 2023

ETS Decision required to keep scheme permanent or revoke and reinstate (Phase 1)

 

No later than June 2023 or 18 months after scheme opening / ETRO