HANOVER LTN PILOT PROJECT: TASKS & TIMELINE
to be delivered over a single phase or a number of phases - dependent on options appraisal outcomes - and budget availability. The first phase would deliver the key LTN measures and modal filters using LTP 2021-22. A second Phase (2022) would allow for complementary measures to be introduced with LTP budget 2022-23
Milestones/tasks |
START |
FINISH |
Procure/access community engagement mapping software |
February 2021 |
April 2021 |
Procure contract and appoint consultancy support |
March 2021 |
April 2021 |
Conduct project data baseline data such as traffic surveys including consultation (stakeholder and community) issues opportunities mapping |
April 2021 |
August 2021 |
Options identification / high level costings / |
May 2021 |
September 2021 |
ETS report - Preferred option / project delivery plan agreed |
October or November (ETS) tbc |
|
Detailed design Phase 1 |
October 2021 |
March 2022 |
Construction |
November 2021 |
December 2021 |
Experimental Traffic Regulation Order (ETRO) consultation (and initial monitoring) period |
December 2021 |
May 2022 |
Phase 2 detailed design |
February 2022 |
March 2022 |
Phase 2 construction |
April 2022 |
May 2022 |
Phase 3 ETRO public consultation period |
July 2022 |
January 2023 |
ETS Decision required to keep scheme permanent or revoke and reinstate (Phase 1) |
|
No later than June 2023 or 18 months after scheme opening / ETRO |